Articulating Compromise As Clock Ticks

722 developers adjust proposal but neighborhood reaction is still mixed

A revised depiction of 722 Williamson with five stories on Williamson, and seven and nine-story towers at the rear. Courtesy: BDG

A revised depiction of 722 Williamson with five stories on Williamson, and seven and nine-story towers at the rear. Courtesy: BDG

Baldwin Development Group (BDG) is determined to build a mixed-use development at 722 Williamson that will honor the Marquette neighborhood planning guidelines and also serve their own commercial interests. However, after Wednesday’s (October 23) meeting with the neighborhood where they presented alternate designs, the way forward is becoming murkier and time is running out.

BDG has met four times with a special Marquette Neighborhood Association (MNA) subcommittee to tweak the design so that it will fit within the guidelines of the Williamson BUILD Plan II that was adopted in 2004. The chief issue is the height of the project, which currently is proposed at 10 stories, giving some pause while others say this is the best kind of infill development for an underutilized space.

In addition to the building height, the subcommittee was concerned about the massing of the building along the bike path which presents both an imposing visage and could cause treacherous conditions in winter due to reduced sunlight possibly causing increased icing on the Capital City Trail. In offering their alternatives, BDG increased the building height on Williamson to five stories and showed eight and nine story options for the main tower that was stepped back from the bike path.

“I think they have made great strides in moving [the proposal] forward from what they had,” said Bruce Woods who chaired the 722 Williamson Subcommittee of MNA’s Preservation & Development Committee. “They listened to a lot of the neighborhood concerns and what they had to say…We as a subcommittee weren’t in place to recommend anything, it was just to help them keep on track with the neighborhood concerns.”

 

What lies beneath

The challenge of an infill development like this is finding the right building to connect with Williamson street, providing parking for residents and tenants while accommodating the 150 parking stalls that are currently serving the three buildings owned by The Rifkin Group, and the Madison Candy Company building owned by John Martens. To replace all that parking at least two levels-worth of parking ramp must be built and structured parking is pricey. To offset this cost, BDG proposed the multi-towered apartment and commercial building.

The orientation of the tower was flipped and reduced to nine stories in this version. The west portion is stepped back to give relief to the bike path. Courtesy: BDG

The orientation of the tower was flipped and reduced to nine stories in this version. The west portion is stepped back to give relief to the bike path. Courtesy: BDG

Large developments usually need Tax Incremental Financing from the City and the more rental units and commercial space can mean a lower TIF request. “Depending on the version, and we’re dialing-in costs, it’s somewhere in the two-and-a half and four Million dollar range,” Bower said.

Those costs start below ground before anything new is built. In a twist of irony, the BUILD II plan calls for buildings or at least facades along the street to match its historical past. On the 700 block the old industrial feel may look cool but there are skeletons below.

Where the parking lot is now used to hold, among other things, petroleum tanks that leaked over many decades. The environmental clean-up is estimated at close to $2 Million and it still might not totally fix the issue.

Baldwin Development Group Principal Jim Bower.

Baldwin Development Group Principal Jim Bower.

“Even with all the pots of money that we have been able to identify…we’re still at a gap, we’re still needing significant TIF support to go underground,” said BDG Member Tom Bergamini.

Berganimi is referring to underground parking which would help lower the height of the building but causes the cost of the project to skyrocket due to the initial and ongoing environmental clean-up costs that could include a water pumping and treatment system in the underground parking structure.

Avista

Nonetheless the prospect of a ten-story building is causing heartburn for some, especially those who live in The Livingston, a condominium and apartment complex on the corner of Livingston and Williamson.

Three residents and at least one business owner from the complex showed at the meeting to express their opposition saying their views of the cityscape will be obliterated.

“This isn’t infill to me, this is overfill,” said Jim Simon who lives in the Livingston. “If somebody needs to do infill here with another project, if this doesn’t work here it needs to fit-in with the neighborhood plan.”

The eight-story configuration has the east and west ends abutting the bike path.

The eight-story configuration has the east and west ends abutting the bike path.

Tom Bergamini responded that their plan serves the entire block which includes parking for four commercial buildings that use the current lots that would be redeveloped. “Any development solution that comes here, that’s the starting point before you get one square foot of additional space. Any other developer that comes in has that same challenge.

Simon, who prefaced his remarks by saying he understood the challenges of the developers, responded that he had to take care of his own. “You have your problems, I have mine. You are making my property less valuable,” Simon said.

That sentiment was expressed by the other Livingston residents who say they purchased their condos with the Build II plan in mind that limited heights to five stories. Although some were not aware that two bonus stories can be awarded for affordable housing, preservation,or structured parking.

 

Stepping Back

To meet the concerns of the neighborhood, BDG asked their architect to complete some additional massing studies on the site to see where heights could be lowered and make less of an imposition on the bike path.

To accomplish a lower height on the main apartment tower an additional floor was added to the building on Williamson to make up for the lost units. The middle tower will remain at seven stories but both an eight and nine story main tower were presented.

722 Subcommittee Member John Coleman expresses concern over how much the mechanical systems and housings will add to the height.

722 Subcommittee Member John Coleman expresses concern over how much the mechanical systems and housings will add to the height.

The nine story design features the most articulation with the tower taking the block C shape that faced Willy Street in the original design and flipping it to face north towards MG&E with the western end setback from the bike path.

The eight story version would not have a set back feature and the east and west ends of the tower would be massed on the bike path.

However the visuals presented were incomplete as they were done just to show basic shapes and heights and were not “skinned” with the final exteriors due to the two-day time frame between the subcommittee meeting on Monday and the P&D meeting.

Comparing these dimensions to the BUILD II plan, which allows five stories and a bonus not to exceed seven stories or 85 feet which ever is lower, BDG assumes that the City would approve the bonus stories.

View the BDG slide presentation here

However, that still means the eight story tower would exceed BUILD II by six feet and the nine story would be 17 feet over. In the eyes of BDG, the eight-story plan would be the heaviest lift since at least 10 rental units would be lost in the height reduction.

 

MG&E opposed

One criteria for the bonus stories is the availability of affordable housing which BDG hopes to have 20 percent of the units at 50 percent of Dane County median income. At the moment the units will be priced at 60 percent.

While 1, 2, and 3-bedroom units will be offered at market rates, it seemed apparent through the question and answer session, that at the moment, only the 1 bedroom apartments would be “affordable housing”. Bower said they are still working with the Wisconsin Economic Development Authority (WHEDA) on how to improve this aspect.

722 Williamson Subcommittee Chairman Bruce Woods.

722 Williamson Subcommittee Chairman Bruce Woods.

Opposition from those within a block of the proposed development has so far been from residents as well as others throughout the neighborhood who want to hold fast to the building guidelines.

However, Madison Gas & Electric, which operates the 100-Megawatt gas-fired Blount Station, sent two representatives to the meeting to provide their input.

Community Services Manager  David Benforado read a statement to the committee in which it highlights the power company’s participation in the formulation of the BUILD II plan and expresses concern of a residential development so close to the power facility without a commercial buffer.

Read the MG&E statement here

“Although we have discontinued coal use and taken measures to mitigate noise, it is still a working power plant. We, and we assume the neighborhood, do not want nearby residents to be unhappy. We believe a commercial space would be a better and more appropriate use of that property,” the statement read.

 

UDC Awaits

If this project is to move forward it has to move pretty fast. Bower says that in the next sixty to ninety days he hopes the approvals will be completed or the project could be in jeopardy. Marty Rifkin, who spoke at the meeting said he is unsure if he would collaborate with Martens on future projects if this one falls through.

Martens also warned that it is risky to think the next developer will take such care to win the hearts and minds of the neighborhood. He noted that the Krupp building, which houses the Livingston Place Apartments, could be built anywhere and adds nothing to the neighborhood. “The building to me does nothing but take up space. This building [722 Williamson] engages the street, it adds to vitality, it would put people on the street,” Martens said.

Ground view of the the development from the Bike Path, which was a big concern due to the massing and potential for icing during winter.

Ground view of the development from the bike path, which was a big concern due to the massing and potential for icing during winter due to reduced solar impact. Courtesy: BDG

But it was Judith Guyot, a past Chairwoman of the UDC, who asked the most salient question of the night: What makes this development so unique that it should be allowed to exceed the parameters of the BUILD plan?

“What we’re trying to do is solve the final piece of the puzzle here, and create a vibrant residential and commercial development that adds to the neighborhood. We’re gonna work on the affordability pieces and try and push it as far as we can,” Bower responded. “We’re trying to create a final infill piece of this block, to finish it off. Thats an integrated development that respects Willy Street and builds a streetscape along Willy Street that holds the entire block together.

Read: Willy Better Urban Infill Development (BUILD) plan

Since MNA’s recommendation only carries so much weight in the City approvals process, the subcommittee was formed to help shape the project as best it can as the City imposes its own requirements on the development. After the meeting, BDG, District 6 Alder Marsha Rummel, and Woods huddled and agreed to determine the next steps after BDG meets with the City next week to discuss the project and its finances.

“This is not a project that will get one hundred percent unanimity in either direction. The question becomes…is this a project that adds to our neighborhood, adds to our city, Bower said. “We’re willing to live with compromises. Any one of these permutations has financial implications and so at the end of the day you have to get a project financed to get it built. We don’t want to be outside the BUILD plan.”

The 722 Williamson Subcommittee.

The 722 Williamson Subcommittee of the MNA Preservation & Development Committee. (L to R, Peter Wolff, Bruce Woods (Chair), Lyndsey Lee, John Coleman, Gary Tipler, Anne Walker, Joshua Clements, Daniel Grossberg, Mike Soref)

 

Related: 722 Willy Developers to Present Project Changes

Related: 722 Willy Working Group Outlines Concerns

Related: MNA Establishes 722 Willy Working Group

Related: Interviewing Wild Orangutans

Related: Gehbardt Proposal Selected for Block 800

Related: Nostalgia or Sizzle for Block 800

Related: Two Union Corners Proposals Now on “Short list

Related: C.D. Smith / EUA Withdraws Union Corners Proposal

Related: Where the Sidewalk Ends

Facebook Twitter

2 thoughts on “Articulating Compromise As Clock Ticks

  1. The development will bring in so many more cars into the Willy Street Neighborhood and the flow of traffic on Willy Street and other streets will be so much greater. Already the number of cars and the speed at which they travel has increased in the neighborhood over the last couple of years, and I find this worrisome.

    Maybe a way to deal with this increase in population and vehicle, if the project goes through at its current expected size, would be to make Willy Street ‘one-way,’ west bound only. Then residents in the new structures would have to utilize East Washington to go east, people coming into the area from the west of the capital would have to drive down East Washington.

    • Diane, I share your concerns about siting 168 to 188 apartment units here. For perspective, that’s still a huge number, while the developers’ original proposal was for 220 units (the same number as the 12-story Constellation on E. Wash). That’s way too much for this site, particularly since City plans already call for such high-rise development to occur on East Wash, not here. If S. Livingston is dead-ended at the railroad crossing, as the State Railroad Commissioner proposes, that will only complicate matters further. Making Willy a One-way, west-bound? To accommodate this project? Sorry, no, that’s asking way too much of us who live at this end of the neighborhood: (1) we get bricked-in by a high-rise, and (2) we get blocked in (or out) of the area by more traffic and whatever work-arounds are tried to attempt to deal with that. I think the simpler solution is one that stays true to both the neighborhood’s and City’s plans and to the character of the historic 4-story buildings on the site in a Landmark district: a high-rise shouldn’t be allowed on the 700-block of Williamson Street.

Leave a Reply to Daniel Grossberg Cancel reply